|
|||||
Project
Management MGMT627
VU
LESSON
17
PROJECT
PLANNING (CONTD.)
Broad
Contents
Elements
of a Project Plan
System
Integration
17.1
Elements
of a Project Plan:
As
we know that the process of
developing project plan varies
from organization to
organization.
However, any project plan
must contain the following
elements:
·
Overview:
This
is short summary of objectives and scope of
project. It is directed to top
management
and
contains statement of goals of project;
brief explanation of their
relationship to firm's
objectives,
description of managerial structure that
will be used for project,
and list of major
milestones
in project schedule.
·
Introduction:
This
contains more detailed statement of general goals
noted in overview section.
Statement
should
include profit and competitive
aims as well as technical
goals.
·
General
Approach:
This
section describes both managerial and
technical approaches to work.
Technical
discussion
describes relationship of project to
available technologies. For
example, it might
note
this project is extension of
work done by company for earlier
project. Subsection on
managerial
approach takes note of any
deviation from routine procedure
for instance, use
of
subcontractors for some
parts of work.
·
Contractual
Aspects:
This
critical section of plan includes
complete list and description of
all reporting
requirements,
customer-supplied resources, liaison
arrangements, advisory committees,
project
review and cancellation procedures,
proprietary requirements, any
specific
management
agreements (for example, use
of subcontractors) as well as
technical
deliverables
and their specifications,
delivery schedules, and
specific procedures
for
changing
any of above. Completeness is
necessity in this section. If in doubt
about whether
item
should be included or not, wise
planner will include
it.
·
Schedules:
This
section outlines various schedules and
lists all milestones events. Estimated
time for
each
task should be obtained from
those who will do work.
Project master schedule
is
constructed
from those inputs. Responsible
person or department head should
sign off on
final,
agreed-on schedule.
·
Resources:
There
are two primary aspects to
this section. First is budget.
Both capital and
expense
requirements
are detailed by task, which
makes this project budget.
One-time costs are
separated
from recurring project
costs. Second, cost
monitoring and control
procedures
should
be described. In additional to usual routine
elements, monitoring and
control
procedures
must be designed to cover special
resource requirements for project,
such as
128
Project
Management MGMT627
VU
special
machines, test equipment,
laboratory usage or construction,
logistics, field
facilities,
and
special materials.
·
Personnel:
This
section lists expected personnel requirements of
project. Special skills, types of
training
needed, possible recruiting problems,
legal or policy restrictions on
work force
composition,
and any other special
requirement, such as security
clearances, should be
noted
here. (This reference to "security"
includes need to protect trade
secrets and research
targets
from competitors as well as need to
protect national security). It is
helpful to time-
phase
personnel needs to project needed and in
what numbers. These
projections are
important
element of budget, so personnel, schedule,
and resources sections can
be
crosschecked
with one another to ensure
consistency.
·
Evaluation
Methods:
Every
project should be evaluated against
standards and by methods established at
project's
inception.
This section contains brief description
of procedure to follow in
monitoring,
collecting,
storing, and evaluating
history of project.
·
Potential
Problems:
Sometimes
it is difficult to convince planners to
make serious attempt to anticipate
potential
difficulties.
One or more such possible disasters
such as subcontractor default,
technical
failure,
strikes, bad weather, sudden required
breakthroughs, critical sequences of
tasks,
tight
deadlines, resource limitations, complex
coordination requirements,
insufficient
authority
in some areas, and new
complex or unfamiliar tasks
are certain to occur.
Only
uncertainties
are which ones will occur
and when. In fact, timing of
these disasters is
not
random.
There
are times, conditions and
events in life of every
project when progress
depends on
subcontractors,
or weather, or coordination or resource
availability, and plans to deal
with
unfavorable
contingencies should be developed early
in project's life cycle. Some
project
managers
disdain this section of plan on grounds
that crises cannot be predicted.
Further,
they
claim to be very effective
firefighters. It is quite possible that
when one finds such
project
manager, one has discovered arsonist. No amount of
current planning can
solve
current
crises, but preplanning may
avert some.
These
are elements that constitute
project plan and are
basis for more detailed
planning of
budgets,
schedules, work plan, and general
management of project. Once
this basic plan is
fully
developed
and approved, it is disseminated to all
interested parties.
Below
is detailed discussion on some
important parts/aspects of a Project
Plan.
·
Introduction/Overview:
The
project management plan
introduction/overview includes an
introduction both to the
specific
project and to the project management
plan document itself. Some
background
information
may be included to set the
stage or provide perspective on the
information that
follows,
such as how the project was
initiated, who the customer or
sponsor is, how the
project
is
funded, or other factors that
are important to those who
read the plan. Introductions
are
always
short, allowing the reader to move
into the plan quickly.
Additional external or
historical
information
can be referenced or included in the
Appendix.
External
factors, such as general or specific economic trends,
constraints, or opportunities;
political
or governmental conditions; population
demographics; or internal
organizational
factors,
should be discussed.
129
Project
Management MGMT627
VU
·
Mission
and Objectives:
The
purpose or mission of the project is
stated in one or two paragraphs,
followed by a set
of
concrete objectives. The mission
statement is all encompassing,
establishing why the
project
exists. Mission statements can be general
or specific. They also reference
the
customer
if the project is being performed
under contract or for a third
party.
Project
objectives are outlined as
specific goals to be accomplished and to
which status they
can
be applied. For instance,
objectives for a small
construction project might
include a
good
location; a modern energy-efficient economic
design; a fully furnished
facility; a
complete
set of project documents;
compliance with all laws,
codes, and requirements; a
standard
profit margin; and a completion
date.
Planning
becomes straightforward when
objectives are defined for
key areas. Objectives
can
be established for every aspect of the
project, including scope of
work, organization,
management,
systems, environment, safety, and
overall completion of the project
(i.e., final
cost
and schedule dates). Established
objectives in the following areas
facilitate detailed
planning,
systems development, and work
performance:
Technical
objectives
o
Schedule
objectives
o
Cost
objectives
o
Organizational/personnel-related
objectives
o
Quality
objectives
o
Environmental
safety and health objectives
o
Contracting/procurement
objectives
o
Management
system objectives
o
Well-defined
objectives enhance the reliability of
subsequent planning. Once
objectives are stated
in
concise
terms, they allow for the
development of the project scope of
work and the work
breakdown
structure.
·
Work
Scope:
The
work scope section of the project
management plan demonstrates
how well the project
is
understood.
It
includes narrative descriptions of all
elements of the project's scope of
work. It clearly
identifies
the products or services to be provided to the
customer. The statement of
work
contains
enough information to allow
development of the Work Breakdown
Structures
(WBS),
schedules, and cost estimates, as
well as assignment of
responsibilities.
This
section can address the
project phases and include
special plans associated with
those
phases,
such as the Research and
Development plan, engineering/design
plans, construction
plan,
manufacturing plan, facility start-up
plan, or transition plan. It
may also describe
the
systems
management activities, including
systems engineering and
integration, to ensure
project
life cycle perspective. In other words,
it shows that the activities
necessary to ensure
that
the design and final products meet
customer requirements are all
planned and managed
properly
and can be integrated and operated as
intended, and that start up,
transition,
operation,
and completion activities are
also planned and managed
properly.
To
simplify preparation, the work
scope can be prepared in outline
form, which can then
be
used
to develop the Work Breakdown
Structures (WBS). Often the
Work Breakdown
Structure
(WBS) and work scope
are prepared in parallel, with the
resultant narrative
description
of the work called a Work
Breakdown Structure (WBS)
dictionary.
130
Project
Management MGMT627
VU
·
Planning
Basis:
The
planning basis section provides
for the documentation of key
approaches, assumptions,
requirements,
and other factors considered during
preparation of the project
management
plan.
The following topics are
addressed in this section:
1.
Project
Deliverables/End Products:
A
list of all products, documents,
and services to be delivered to the
customer
over
the life of the project is
required.
2.
Requirements:
Requirements
are specifications or instructions
that must be followed
during
project
performance.
They
may include technical requirements,
facilities requirements, data
requirements,
management requirements, or special instructions.
Technical
requirements
may include codes,
standards, laws, engineering or
design
specifications,
models, or examples for mandatory or
recommended compliance
on
the project. When there are
mandatory requirements, such as laws,
these
must
be identified and listed, or project
performers run the risk of
noncompliance
and legal prosecution.
Facilities
requirements include an initial
assessment of types, amount, and
quality
of facilities needed for the
project, along with related
utilities, furniture,
and
equipment.
This
provides initial bases for
estimating quantities and
costs associated with
those
resources. Overlooking facilities
issues during project
planning leads to
schedule
slippages, cost overruns, unhappy
project participants, and
untold
headaches
for the project managers.
For small projects, facility
requirements
may
not be a big issue; for
larger projects, they can be
critical.
Functional
and operational requirements spell out
what the system, facility,
or
product
being produced is intended to do.
They provide the basis for
the
engineering,
design, and planning of the system,
facility, or product. Where
Functional
and operational requirements exist,
listing or identifying them
greatly
simplifies and facilitates
the design process. Mandatory
data
requirements,
management directives, or special
instructions are also
identified
and
documented during the planning process.
Special instructions may
include
directions
from the customer or upper
management or may be spelled
out in
contract
documents.
3.
Constraints:
Constraints
may include known technical
limitations, financial ceilings,
or
schedule
"drop dead" dates. Technical
constraints may be related to
state-of-
the-art
capabilities, interface requirements with
other systems, or user-related
issues
(e.g., software that must
run on certain types of personal
computers).
Financial
and schedule constraints can be
introduced by the customer and
lead-
time
associated with procured hardware or
funding/ budgetary
limits.
131
Project
Management MGMT627
VU
4.
Approaches/Strategies:
The
approach or strategies to be utilized can
have a major impact on
subsequent
planning.
For
instance, if all project work is to be
performed within the parent
(host)
organization
with minimum subcontract support that
approach impacts planning
of
resources and organizational issues. If
work is to be "fast-tracked" by
overlapping
design and construction activities, or by
performing more work in
parallel,
then that approach can be described.
Communication of strategies to
project
participants can be done effectively by
devoting several paragraphs to
that
topic in this section of the project
management plan.
5.
Key
Assumptions:
Every
project is planned under
some degree of uncertainty.
Therefore,
assumptions
are required to estimate
work scope, schedule
durations, resource
requirements,
and cost estimates.
Assumptions are also
required when
defining
the
management strategies, systems,
and procedures to be
utilized.
Major
assumptions are to be documented because
they can have a
significant
impact
on planning and estimating. This is
true on all projects, regardless
of
size.
Large projects, which involve
numerous participants and
major
complexities,
generally depend on more key assumptions
during project
planning
than smaller projects. The major reason
for documenting key
assumptions
is to provide the project manager
with a basis for revising
plans
when
the assumptions are changed
(that is, when a customer
changes his or her
mind).
6.
Specifically
Excluded Scope:
This
subject may be needed to limit the
scope of work. It highlights
specific
and
relatively obvious issues,
such as documentation, training, or
follow-on
support,
which customers often assume
but which cost money and
have not
been
included in the project plan.
Clarification of these scoping questions
saves
headaches
later, in some cases even
avoiding litigation.
17.2
Systems
Integration:
Systems
integration (sometimes called
systems engineering) plays
crucial role in performance
aspect
of project. We are using
this phrase to include any
technical specialist in science or art
of
project
who is capable of performing
role of integrating technical
discipline to achieve
customer's
objectives, and/or integrating
project into customer's
system.
As
such, system integration is concerned
with three major
objectives:
1.
Performance:
It
is what system does. It
includes system design, reliability,
quality, maintainability,
and
reparability. Obviously, these
are not separate,
independent elements of system,
but
are
highly interrelated qualifies. Any of
these system performance characteristics
is
subject
to over-design as well as under-design
but must fall within design
parameters
established
by client. If client approves, we may
give client more than
specifications
132
Project
Management MGMT627
VU
require
simply because we have already designed
to some capability and giving
client
over
designed system is faster and less
expensive than delivering
precisely to
specification.
At time, esthetic qualities of system
may be specified, typically
through
requirement
that appearance of system
must be acceptable to
client.
2.
Effectiveness:
Objective
is to design individual components of
system to achieve desired performance
of
optimal manner. This is accomplished
through following
guidelines:
·
Require
no component performance specifications unless
necessary to meet one or
more
system equipments.
·
Every
component requirement should be traceable to one or
more systems
requirements.
·
Design
components to optimize system
performance, not performance of
subsystem.
It
is not unusual for clients to
violate any or all of these
seemingly logical
dicta.
Tolerances
specified to far closer
limits than any possible
system requirement,
superfluous
"bells and whistles," and "off
shelf" components that do
not work well
with
rest
of system are so common they
seem to be taken for granted by
both client and
vendor.
Causes of these strange
occurrences are probably
associated with some
combination
of inherent distrust between buyer and
seller, desire to over-specify
in
order
"to be sure" and feeling
that "this part will do
just as well". These
attitudes can be
softened
and replaced with others that
are more helpful to process of
systems
integration.
3.
Cost:
Systems
integration considers cost to be design
parameter, and costs can be
accumulated
in several areas. Added design cost
may lead to decreased
component
costs,
leaving performance and effectiveness
otherwise unchanged. Added design
cost
may
yield decreased production
costs and production cost
may be traded off against
unit
cost for materials. Value
engineering (or value analysis)
examines all these
cost
tradeoffs
and is important aspect of systems
integration. It can be used in
any project
where
relevant cost tradeoffs can
be estimated. It is simply consistent and
thorough use
of
cost/effectiveness analysis. For application of
value engineering techniques
applied
to
disease control projects.
Systems
integration plays major role
in success or failure of any
project. If risky
approach
is taken by systems integration, it
may delay project. If approach is
too
conservative,
we forego opportunities for
enhanced project capabilities or
advantageous
project
economies. Good design will
take all these tradeoffs
avoid locking project
into
rigid
solution with little
flexibility or adaptability in case
problems occur later on or
changes
in environmental demand changes in
project performance or effectiveness.
133
Table of Contents:
|
|||||