|
|||||
Project
Management MGMT627
VU
LESSON
15
PROJECT
PLANNING
Broad
Contents
Introduction
Project
Planning
Plan
of Execution
Information
Required for Planning
Execution of Projects
Early
Stage Documentation by Project
Manager
15.1
Introduction:
Planning
is done to facilitate later accomplishment.
Planning techniques covered here
are
intended
to smooth the path from idea
to accomplishment. Project planning is a
complicated
process
to manage project and
planning act as map of this
process. Map must have
sufficient
detail
to determine what must be done
next but simple enough
that workers are not
lost in welter
of
minutiae.
Almost
all project planning techniques
lead to plans that contain
same basic elements.
They
differ
only in ways they approach process of
planning. At its best,
planning is tortuous. It is
iterative
process yielding better plans
from not-so-good plans, and iterative
process of
improvement
seems to take place in fits
and starts. Process may be
described formally, but
it
does
not occur formally. Bits
and pieces of plans are
developed by individuals, by formal
group
meetings,
or by formalized planning teams and
then improved by other
individuals, groups, or
teams,
and improved again, and
again.
15.2
Project
Planning:
In
order to do successful project
management, (whether it is in response to
an in-house project
or
a customer request), it must
utilize effective planning techniques.
The quantitative and
qualitative
tools for project planning
must be identified. Management
must make effective
utilization
of resources, from a systems
point of view.
A
systematic plan is required in
which the entire company is considered as
one large network
that
is further subdivided into smaller
ones. This would ensure
effective utilization over
several
different
types of projects.
In
this regard, the first step in
total program scheduling is to understand
the project objectives.
These
goals may be to:
·
Develop
expertise in a given area
·
To
become competitive
·
To
modify an existing facility
for later use
·
To keep
key personnel employed.
Both
implicitly and explicitly, the objectives
are generally not
independent and are
all
interrelated.
The
following four questions must be
considered, once the objectives are
clearly defined:
i)
Which
functional divisions will
assume responsibility for accomplishment
of these
objectives
and the major-element work
requirements?
ii)
The
required corporate and organizational
resources available?
119
Project
Management MGMT627
VU
iii)
What
are the major elements of the
work required to satisfy the
objectives, and how
are
these
elements interrelated?
iv)
What
are the information flow requirements
for the project?
Both
the direct as well as the
indirect-labor-charging organizational
units must accomplish
careful
planning and analysis, if the project is
large and complex. The
project organizational
structure
must be designed to fit the project;
work plans and schedules
must be established so
that
maximum allocation of resources
can be made; resource
costing and accounting
systems
must
be developed; and a management
information and reporting system
must be established.
Unless
all of the necessary information
becomes available at project
initiation effective
total
program
planning cannot be accomplished. These
information requirements are:
·
The
statement of work
(SOW)
·
The
project specifications
·
The
milestone schedule
·
The
work breakdown structure
(WBS)
As
the name indicates, the statement of work
(SOW) is a narrative description of the
work to be
accomplished.
It includes the objectives of the
project, a brief description of the
work, the
funding
constraint if one exists, and the specifications and
schedule. The schedule is a
"gross"
schedule
and includes such things as
the:
·
Start
date
·
End
date
·
Major
milestones
·
Written
reports (data items)
Report
writing is a specialized area. Written
reports should always be identified so
that if
functional
input is required, the functional
manager will assign an
individual who has
writing
skills.
It is no secret who would
write the report if the line
people did not.
15.3
Planning
of Execution:
As
described earlier, project planning is a
structured sequence of events that
lead to a desired set
of
objectives.
A
detailed, written, "Plan
of Execution (P of E) " for
project is drawn up, once
project
viability
has been established and decision to
proceed has been made.
This plan must show:
a)
Who
is to do what
b)
When
c)
How
d)
Major
decisions requirements
It
is essential that the project
objectives must be clearly
tied to overall mission of the
firm.
Senior
management defines a
firm's:
·
Intent
in undertaking project
·
Scope
of project
·
Project
desired results
In
this regard, the Plan of
Execution:
·
Becomes
a vehicle for communication
with all stakeholders
120
Project
Management MGMT627
VU
·
Becomes
a prerequisite for detailed
scheduling of work
·
Helps
documentation for preparation of
"cost estimates"
Project
management plans are more comprehensive
than either management plans or
project
plans.
The preparation of plans is a simple,
straightforward approach designed to promote
and
ensure
comprehensive project planning. The
project management plan is a
combination of two
plans
that are often prepared separately: the
traditional management plan,
which describes
operational
management systems and approaches, and
the project plan, which
includes the work
breakdown
structure (WBS), logic, schedules,
and cost estimates. They
reflect awareness
that
the
people, the system, and the
detailed planning are all
critical to project
success.
15.4
Information
Required From Planning of
Execution:
Following
information is required:
1.
Type
of project
2.
Its
capacity and
location(s)
3.
Scope
of work to be performed
4.
Preliminary
cost estimation
5.
Site
visitation report
6.
Preliminary
schedule of major
objectives
7.
Pertinent
contract requirements
8.
Special
design and/or construction
requirements
9.
Climate
restrictions
10.
Environmental
study, feasibility study reports,
etc
11.
Proposal
document
Following
are the basis for Project
Manager's planning endeavors
for planning of
execution.
·
Existing
documents:
·
Client's
inquiry
·
Proposal
(as modified/amended in negotiation
period)
·
Contract
and preliminary wok plans (during
proposal preparation)
·
Before
Execution Planning:
Before
Execution Planning, project
manager is required to provide the
complete scope
definition
of work.
Planning
of Execution provide basis
to:
a)
Schedules
b)
Detailed
cost estimation
c)
Control
budget
d)
Quality
and performance assurance program
It
leads to develop Work
Breakdown Structure and integrates work
schedule costs into
track-
able
and controllable program. During
this phase, performance baselines
are also estimated
during
project planning.
15.5
Early
Stage Documentation by Project
Manager:
This
includes:
1.
Coordination
Procedure (CP):
·
Coordination
Procedures or Job Instructions. It
includes administrative procedures
in
projects.
121
Project
Management MGMT627
VU
2.
Early
Work Schedule (EWS):
·
This
helps in tracking activities requiring
immediate action.
·
Cannot
wait for release of formal
schedules.
·
Early
work Schedule (EWS) contains:
a)
Running list of activities
started early
b)
Name of responsible individuals
c)
Completion date of an
activity.
15.5.1
Emphasis Placed on Early
Planning:
As
we know that planning does
not stop with the initial
plan. It is a continuous
process
which
is fine tuned whenever
necessary. Many events can
potentially adversely
affect
/disrupt
plan targets. In this regard,
many a times, corrective actions will be
required to
restore:
a)
Integrity
of schedule
b)
Budget
15.6
Example
of Building House to Common
"Activities in Each Phase" of Project
Planning:
1.
Definition
Phase:
Problem
defined in request document
House
need heating, plumbing,
lighting, storage
etc.
2.
Analysis
Phase:
Produces
functional specifications
(deliverable)
Location
of ventilators, air conditioner,
outlet for phone etc.
3.
Design
Phase:
System
proposed to solve problem
System
divided into functional
components
Components
are interconnected
Expectation:
rooms, ventilation, wiring
etc.
4.
Programming
Phase:
Actual
work conducted to bring system
into being.
Expected:
building of house
5.
System
Test Phase:
Brings
pieces together and tests
them as whole
House:
test plumbing, electricity,
roof, etc.
6.
Acceptance
Phase:
Customer
tests complete system for
acceptance/ payment
Minor
problems are fixed
Major
problems require negotiation
Minor
problem may include house
buyers ask for repairs to cracked
plaster, or outlet
Major
problem can be two
fireplaces vs. one
built.
7.
Operations,
Installation and
Use:
House
buyer moves in and lives in
house
Problems
developed/found upon use are
fixed during warranty
period
Not
included in this are:
a)
Maintenance
b)
Upgrades
c)
Extensions
122
Table of Contents:
|
|||||