|
|||||
Project
Management MGMT627
VU
LESSON
13
PROJECT
PROPOSAL
Broad
Contents
Characteristics
of a Project Proposal
Preparation
for Future Proposal
Proposal
Effort for Specific
Proposals
Proposal
Efforts
Typical
Engineering, Procurement and Construction (EPC)
Proposal Contents
Modifications
to the Standard Proposal
13.1
Characteristics
of a Project Proposal:
The
more important characteristics of a
project proposal are:
1.
Proposal projects are high priority,
short duration efforts. They
must be completed to the
owners
schedule requirement regardless of the
work load and other demands
on the
contracting
organizations.
2.
The owner's specifications
for the preferred payment method
must be adhered to, at least
in
the
basic proposal. Alternates
which offer benefits to both
parties may be suggested for
the
owner's
consideration.
3.
The owner frequently will
specify a particular format
for the proposal and for
presentation
of
the requested information.
4.
The owner may express a
clear preference as to the location where the project
work will be
done.
The engineering company may
suggest alternate arrangements that
give the owner a
more
cost effective project
without sacrificing the required
contract. The base
proposal
however,
must be as responsive as possible.
5.
The owner may have a preference,
openly expressed or merely
implied, for the
construction
labor
arrangement. If this preference has not
been made clear in the Request
for Proposal
(RFP)
or in the discussions with the owner, it
should be determined at the earliest
possible
time
in the proposal effort so that the
proper construction program
may be planned.
6.
A proposal project requires forming a
team of the representatives for
sales, project
management,
technical and support functions. Many of
these have responsibilities over
and
above
the proposal project. These
work loads must be considered and
respected insofar as is
possible.
7.
Proposal projects are normally costed
against corporate overhead and therefore will
be
tightly
budgeted and be closely monitored by senior
management.
13.2
Preparation
for Future
Proposal:
Because
of the price restraints and the
repetitive nature of much of the data
used in proposals, it
is
helpful to collect as much as possible of
the proposal information in advance.
This is
especially
true for the following
areas:
·
Proposal
project manager should be
identified in advance. In a company with
a significant
continuing
proposals load, a group may
be formed consisting of former
project managers
with
verbal skills and the proper
personality to allow them to function in
the pressure
107
Project
Management MGMT627
VU
cooking
environment of proposal preparation.
These individuals must have a
high tolerance
for
working under tight
schedules, stringent budgets,
with borrowed personnel, and
being
the
object of continual criticism
which is not always
constructive.
·
A
proposal publication staff
should be in place to be fully effective.
These individuals
should
have skills in editing, use of
word processing and reproducing
equipment, as well as
graphic
art capability. They should
be able to work effectively
with the masses of
material
in
various stages of progress to
assure that all of it comes
together according to the
schedule.
·
A
technical information data
base including the full
range of the type of projects offered
by
the
company, including feasibility
studies, engineering projects, as well as
full scope
projects
for various types of
facilities.
·
Standard
scope of services should be
developed that can be
readily customized for
the
particular
project on word processing
system. Much of the particular
information of various
projects
is quiet similar and only requires
bringing it into conformance with
owner's
requirements
or with those of particular
facility of location.
·
The
company should have developed comprehensive
definitions for the various
levels of
efforts
associated with producing
cost estimates of various
accuracies. This is
particularly
important
for developing proposals for
feasibility studies.
·
Work
plans should also be developed
for the various basic types of projects.
These can be
of
general information which can
then be modified to conform to
the plans for the
specified
project
under consideration.
·
A
data bank is helpful to standardize
commercial terms and conditions
together with listing
that
define those costs included
in overhead and those which are
not. This is
particularly
important
in reimbursable contracts to control
charges to the standard check
list and the
resultant
changes in the reimbursable unit
cost.
·
Qualification
material should be updated frequently in
several different standard formats
such
as:
Project
performance data, schedule and
cost
o
Descriptions
of past projects
o
Resumes
of key personnel
o
Write
ups on support areas such
as:
o
Project
Controls
Procurement
Procedures
Material
Management
Quality
Assurance Practices
·
Typical
write ups should be prepared in
advance for various other
parts of the proposal.
These
will be modified to suit the
Request for Proposal (RFP) or inquiry
document. Among
other
these writings
include:
o
Introduction
o
Project
Organization
o
Schedule
o
Project
Controls
o
Compensation
108
Project
Management MGMT627
VU
13.3
Proposal
Effort for Specific
Proposals:
Preparation
of the proposal may start as
soon as there has been a
positive indication that
the
company
will be included in the bid
list and preliminary information is
available on the project.
Early
efforts would
include:
·
Preliminary
assignments for the anticipated proposals
would be made based upon
the
schedule
for the Request for Proposal (RFP)
release and the due date of the
proposal. These
assignments
would include the proposal
project manager, the project manager
proposed to
head
the project, and the proposal publication
and technical support personnel. In
addition,
the
lead estimator, the lead scheduler,
technical personnel, procurement and
construction
representatives
as indicated by the nature of the effort
would be selected.
·
The
preliminary proposal plan
schedule and budget should be
blocked out. The
proposal
plan
would define the outline of the
proposal and the preliminary assignment
of the work.
The
schedule would indicate
dates for completion of the
preliminary draft, job hours
and
cost
estimates, the final draft
dates, the necessary dates
for approval, and the
publication
and
delivery dates.
·
A
rigorous assessment should be
made of the technical aspects of the
project to identify the
company's
strengths and weaknesses.
Immediate and specific actions should be
planned to
boost
capability where this is required
and to develop the personnel and
background
information
to cover these critical
areas.
When
Request for Proposal (RFP) is received,
it is reviewed and a bid/no bid
decision is made.
13.4
Proposal
Effort:
1.
Assignment
of Proposal to Team Members:
As
soon as decision to bid has
been confirmed, the assignment of
team members is
finalized.
2.
Kick-Off
Meeting:
The
project manager calls a kick-off
meeting, at which the time
task assignments and
the
corresponding schedules are
made. At this meeting,
technical, legal and
compensation
considerations are reviewed and
assignments of responsibilities are
made.
3.
Preliminary
Review of the Proposal
Text:
All
material is typed on word
processor, with margins for
easier editing. Typed
drafts
should
be checked carefully against the original
draft to assure that nothing
has been
inadvertently
omitted.
4.
Final
Review:
When
text is essentially in final
form and all changes have
been incorporated, it is
submitted
for review of operations management and
for final legal review. All
major
changes
from this last text review
should be flagged so that the
signoff should be
obtained
quickly.
5.
Publication
and Signoff
6.
Delivery
of the Proposal
109
Project
Management MGMT627
VU
13.5
Typical
Engineering Procurement and Construction (epc)
Proposal Contents:
Following
is the summary of the typical contents of
cost reimbursable proposal for
Engineering,
Procurement
and Construction services.
1.
Introduction
and Summary:
The
Request for Proposal (RFP) conditions
are summarized and general approach to
the
work
by the contractor is indicated.
2.
Project
Description:
This
material is largely taken
from the Request for Proposal (RFP). It
may also include
information
that has been obtained by
site visits, during pre-bid conference,
and in other
contacts
with the owner of other
knowledgeable sources.
3.
Scope
of Services:
This
section details the services the owner
will provide. It includes the
services that will
be
performed and the documents that
will be produced. All services should be
well
defined,
not opened, even in reimbursable proposals. All of the
documents that are to
be
furnished as part of the services of the
contractor should be listed in
detail. A brief
description
of what each will include
should also be
provided.
4.
Work
Plan and
Schedule:
The
project work plan is
developed in response to the stated
objectives of the owner or
as
defined by the sales representatives and the
objectives of the contracting firm
for the
specific
proposal. It may be presented in
graphic form for showing the
interrelationship
between
various activities.
5.
Project
Organization:
This
describes the proposed project
organization, and details the
responsibilities of each
of
the key member of the project
team. An organization chart depicting the
proposed
project
team will be drawn. The
interface with the supplier of
technology should be
carefully
defined, and the technical review
responsibilities should be carefully
defined.
6.
Estimates,
Hours, Costs:
All
of the information presented in the
previous sections of the proposal
must be taken
into
account in preparing the estimates of
work. The cost estimates
will include salaries
of
all technical and non
technical personnel, as well as indirect
costs such as travel,
communication,
computer use and reproduction.
7.
Compensation:
After
the estimates have been reviewed, the
commercial terms are
finalized by adding
those
discretionary figures such as burdens,
contingencies, overlays and fees
required
by
the format of the bid. This
information is presented in the compensation section
of
the
bid.
8.
Qualifications:
The
qualification section of the proposal contains
all relevant material arranged
in
proper
manner to strengthen confidence as to the
contractor's capability in the mind
of
the
owner's management. It must
always be reviewed to ensure
that the information
presented
is accurate, pertinent and
forceful.
13.6
Modifications
to the Standard
Proposal:
Many
owners have a very specific format
which requires that the contractor depart
from a
standard
proposal format. It is best to
follow the specified format as it
will help to simplify
the
proposal
evaluation process in the owner's
office.
110
Table of Contents:
|
|||||